1,547
Mapped facilities · 46 states
394.6 GW
Tracked demand · 68% of U.S. load
623
Data-center bills · 45 states
96
Frontier data centers tracked

Executive summary

The U.S. AI data-center buildout continues to be defined by one binding constraint: power. As of Nov 8, 2026, we track 1,547 data-center facilities mapped from OpenStreetMap across 46 states, 394.6 GW of total U.S. grid demand across 7 ISO/RTO markets (~68% of U.S. load; data centers are a growing share, not the whole), and 623 data-center–related legislative items across 45 states plus 58 federal. On the frontier, Epoch AI tracks 96 leading-edge data centers totaling roughly 15.1 GW of power.

Geographic concentration remains extreme: Virginia leads with 342 mapped facilities, and the top five states account for the bulk of activity. The leading generation source on the grid right now is Natural Gas at 43.8%. Policy is the emerging variable — moratoriums, zoning, and ratepayer-impact bills are rising across states as communities weigh the load growth.

Facilities & geography

Top states by mapped data-center facilities (OpenStreetMap, ODbL):

StateFacilitiesShare
Virginia34222.1%
Texas1409.0%
Oregon1338.6%
California1117.2%
Ohio905.8%
Washington654.2%
Arizona613.9%
Iowa593.8%
Illinois513.3%
New Jersey483.1%

Power & grid demand

Live electricity demand by ISO/RTO (EIA), totaling 394.6 GW across 7 markets. The California ISO daily peak is roughly 26 GW.

ISO / RTODemand (GW)
PJM83.3
MISO67.2
ERCOT44.4
SPP29.1
CAISO19.1
NYISO13.5
ISO-NE10.7

U.S. generation mix (share of output):

SourceShare
Natural Gas43.8%
Nuclear19%
Coal16.7%
Wind7.2%
Solar6%
Hydro5%
Other2.2%

Policy landscape

623 tracked data-center bills across 45 states and 58 federal items (LegiScan, CC BY). States with the most activity:

StateTracked bills
Virginia61
New Jersey50
Michigan50
Pennsylvania49
Minnesota33
New York24
Illinois24
Tennessee19

Capital & companies

Recent tracked deals, financings, and PPAs:

CompanyEventDate
GoogleAlphabet's $15 Billion Investment in Malaysia Data Centers Shows That Midterm…2026-11-08
GoogleGoogle Plans A $17 Billion Wyoming Data Center Run On Fuel-Cell Power2026-11-07
—Lanarkshire AI datacentre to fully rely on National Grid despite renewables c…2026-11-07
—An unexpected activist emerged to help block a $5 billion data center in Mary…2026-11-07
Google / CrusoeGoogle buys the Wyoming data center Crusoe couldn't finish on its own2026-11-07
MetaMeta chief strategy officer Dave Wehner leaves to join AI infrastructure star…2026-11-07
MicrosoftMicrosoft (MSFT) Is Pulling Back From Key Neocloud Data Center Deals2026-11-07
Google / CrusoeGoogle acquires Wyoming data center site from AI infrastructure firm Crusoe2026-11-06

Recent SEC filings referencing data centers (EDGAR):

CompanyFormDate
TERAWULF INC. WULF8-K2026-11-06
TERAWULF INC. WULF10-Q2026-11-06
IRON MOUNTAIN INC IRM8-K2026-11-05
Core Scientific, Inc./tx 10-Q2026-11-05
IREN Ltd IREN8-K2026-11-05
Core Scientific, Inc./tx 8-K2026-11-05
IRON MOUNTAIN INC IRM10-Q2026-11-05
Hut 8 Corp. HUT8-K2026-11-04

Frontier compute

The largest known frontier data centers by reported power capacity (Epoch AI, CC BY 4.0); Epoch also tracks 3,708 notable AI models:

FacilityOperatorMWCountry
Anthropic-Amazon New CarlisleAmazon1,037United States
Colossus 2xAI946United States
OpenAI Stargate AbileneOracle824United States
Microsoft Fairwater AtlantaMicrosoft636United States
DayOne Nusajaya—473Malaysia
Meta PrometheusMeta471United States
DayOne Kempas—422Malaysia
Microsoft Fairwater WisconsinMicrosoft369United States
Google Pryor (North)Google368United States
Colossus 1xAI340United States

Methodology & sources

This report is generated from the same data behind the live dashboards, aggregated from available public sources and proprietary data feeds: facility locations from OpenStreetMap (ODbL); electricity demand and generation mix from the U.S. EIA; legislation from LegiScan (CC BY); deals, equities, and SEC filings via market-data and EDGAR feeds; and frontier-compute figures from Epoch AI (CC BY 4.0). Figures reflect the data as of Nov 8, 2026 and update as the underlying sources refresh. See the full methodology. This report is informational only and not investment advice — see our disclaimer.

About this report

“State of the U.S. AI Data-Center Buildout” is a free, regularly-updated report synthesizing our facility, power, policy, capital, and frontier-compute data into one sourced snapshot, as of Nov 8, 2026. Explore the underlying data on the map, power, policy, and markets pages.